We are getting closer to reopening, but next week matters. Two sections of the Remutaka Rail Trail will be closed at the same time. This is the latest status for 17–30 October. Any changes will be shared next Friday.
For background on the full route, see our Remutaka Cycle Trail guide and the trail map.
Weekends stay open
The track is fully open this weekend, Saturday 17 to Sunday 18 October, and again over Labour Weekend, 24–26 October.
Weekday closures
- Cross Creek Yards to Cross Creek carpark: closed from 7am Monday 19 October to 4pm Friday 23 October
- Siberia Bridge to Cross Creek Yards: closed from 9am Monday 19 October to 4pm Wednesday 21 October, and possibly Thursday if the work needs another day
- Cross Creek Yards to Cross Creek carpark: closed again from 7am Monday 27 October to 4pm Friday 30 October
Why the track is closed
The full closure next week is needed for two jobs.
On the narrow Cross Creek section, the new gravel surface is being laid. Machinery will bring in gravel, dump it, and compact it. That work is expected to take about two weeks.
From Monday 19 to Wednesday 21 October, and possibly Thursday, contractors will also be on the Incline between Siberia Bridge and Cross Creek Yards for a vegetation cutback. Large machinery will be on the trail, with spotters on either side enforcing the closure while the machines are in place.